July 13, 2005
Work started without permit
Massey began construction on coal silo before approval
Advertiser

State regulators allowed Massey Energy to start building a new coal silo more than two months before permits for the project were approved, Department of Environmental Protection records show.

Contractors for Massey subsidiary Goals Coal Co. began work on the silo — proposed for 260 feet from Marsh Fork Elementary School at Sundial — in early April, according to DEP records.

Environmental Protection Secretary Stephanie Timmermeyer did not approve the final permits for the Raleigh County project until June 30.

By then, Goals Coal had already completed the foundation for the 10,000-ton silo, records show.

DEP officials say they did not object because Massey planned only to build the foundation, and not the 168-foot-tall silo itself.

“This was just pouring concrete on the ground,” said Keith Porterfield, an assistant director at the DEP Division of Mining and Reclamation’s Oak Hill office.

Some Raleigh County residents are upset about the silo, and worried about Massey’s continued operation of a preparation plant and huge slurry impoundment so close to an elementary school.

On June 30, Timmermeyer approved a mining permit change and an air permit to allow the silo and a permit renewal for continued operation of the slurry impoundment.

Generally, coal mining operations are not allowed within 300 feet of schools. But DEP says this site is exempt from that limit because it existed prior to passage of the 1977 federal strip mining law.

Last week, Gov. Joe Manchin promised to look into relocating the school and investigate concerns that students, nearby residents and workers are being made sick by chemicals used in the coal preparation plant.

Manchin got involved to convince Rock Creek resident Ed Wiley, whose granddaughter attends the school, to end a sit-in protest on the Capitol steps.

The governor has said he would not “second-guess” DEP’s decision to permit the Massey operation. But Manchin also said he instructed his staff to meet with state regulators “to make sure they have done what they were supposed to do.”

Goals applied for permit changes to allow it to build a second silo to store coal before it is shipped.

DEP officials viewed the move as a positive one. Massey planned to replace an open coal stockpile with a covered silo, reducing potential dust emissions, DEP officials said.

In an April 8 letter, Massey official Danny Cox informed DEP of the company’s “plan to initiate foundation work which will be in full compliance with current permits and applicable regulations.”

“Contractors to construct silos are currently very difficult to retain,” Cox wrote.

“However, Goals has the opportunity to contract construction of the silo if foundation work can begin within the next several days,” he wrote. “Otherwise, construction may be delayed several months and likely into winter.”

Cox said changes to the site’s surface mining and water pollution permits were not needed for the foundation work.

“The work will simply involve foundation construction within a currently permitted and bonded area,” Cox wrote. “The area is already permitted as a preparation plant work area, it is covered by sediment control, and there will be no activities that are not covered by those permits.”

Report a violation or offensive comment.
[X] Close
to report abuse.
Advertisement - Your ad here
In West Virginia, mining companies are literally moving mountains to uncover valuable, low sulfur coal reserves. Mountaintop removal has become the dominant form of surface mining in the state. Coal operators are blasting off hilltops, and dumping leftover rock and dirt into nearby valleys. An untold amount of the state has been flattened, and hundreds of miles of streams have been buried. Find out more in this Special Report.
Advertisement - Your ad here
Advertisement - Your ad here
Inside wvgazette.com